jia-heper

SPREAD SHEET

Task Start Date Duration End Date                        Cost Estimations    
Earth excavation 8/1/2014 2 8/3/2014     elements units per unit cost Total  
laying cement concrete in foundation 8/4/2014 6 8/10/2014     labor 20 $80 $1,600  
placement of steel bar net 8/11/2014 3 8/14/2014     cement 350 $50 $17,500  
laying cement concrete  8/15/2014 1 8/16/2014     steel metal 100 $70 $7,000  
work curing and earth refilling  8/17/2014 2 8/19/2014     concrete 9 $20 $180  
tying rings around vertical steels 8/20/2014 4 8/24/2014     supervision 4 $120 $480  
fixing form work 8/25/2014 2 8/27/2014     TOTAL     $26,760  
laying cement concrete 8/28/2014 4 9/1/2014              
curing RCC column 9/2/2014 2 9/4/2014

 

 

 

           

ORIGINAL ASSIGNMENT

 

Use Microsoft Excel to create a cost estimate for the concrete and structural framing portions of a building project of your choosing. Select the location, size, and type of project. All necessary material, equipment, and labor costs are to be included.

Next, use Excel to create a schedule for the project from start to finish. The schedule will focus on activity sequence, duration, and the critical path.

Accompany the estimate and schedule with a paper summarizing calculations and detailing how activity durations and critical path were derived. Also discuss local constraints, building codes, and OSHA requirements affecting the project.

Support your work with references to the online course material, text, personal experience, and other outside sources if necessary. Properly cite all sources using the APA format.

                   

 