Assume the following project is being prepared for progress review at the end of the third quarter

    November 3, 2024

According to the budget baseline, all tasks should be completed except Task 8, which should be about 30% complete at this time. The project manager reports, however, that all tasks are completed except Task 8, which is only about 10% complete.
Required: Assuming that actual costs to date total $240,000, compute (formula with the result) and evaluate (in narrative form) the following:
a. BAC
b. BCWS (PV)
c. EV
d. AC
e. CV and CPI
f. SV and SPI
g. ETC and EAC
h. TCI.
路 Write a paper of at least 1000 content words, typewritten in double-spaced format (12-point font Times New Roman), page margins Top, Bottom, Left Side and Right Side = 1 inch, including all pages, with reasonable accommodation being made for special situations and online submission variances.
路 Show all work (math steps), including formula, result, and your analysis of the result. (See Appendix B in the text for example formulas.)
路 Discuss, in general terms, a possible change to the project that could be made to hasten the completion of a task that is behind schedule, such as Task 8.
路 Prepare this assignment according to the APA guidelines, including a title page, an introduction, and a conclusion. An abstract is not required. Cite in text and include a References section. A template is included in week 1.
路 In your report, make certain that you include at least two outside references from scholarly sources (from the APUS Online Library)
路 For full credit, make sure that your Similarity Index does not exceed 20%.
路 In the Assignment dropbox, please attach your paper as a file, do not copy